Calligra/Schedules/KOffice/2.2/Release Plan

From KDE Community Wiki

Freezes

Soft-freeze, January, 13th 2010

Soft-freeze will start on January, Wednesday 13th 2010. After soft-freeze, no new feature that is not indicated in the feature plan can be added to KOffice. The list of features is also available.

Hard-freeze, March, 3th 2010

Hard-freeze will start on March, Wednesday 12th 2010. After hard-freeze, no new feature can be added, only bug fixes are accepted. Strings can still be modified until String freeze.

String-freeze, March, 24th 2010

The date for string freeze, at which points it is not allowed to change or add strings, without prior agreement with l10n team.

Beta

Beta 1

  • Tagging on March, 12st 2010
  • Release on March, 16th 2010

Beta 2

  • Tagging on April, 2th 2010
  • Release on April, 6th 2010

Release Candidate

RC1

  • Tagging on April, 23rd 2010
  • Release on April, 27th 2010

Final release and maintenance schedule

2.2.0

  • Tagging on May, 21th 2010
  • Release on May, 26th 2010

2.2.1

  • Tagging on June, 25th 2010
  • Release on June, 30th 2010

2.2.2

  • Tagging on August, 20th 2010
  • Release on August, 25th 2010