Calligra/Schedules/2.9/Release Plan: Difference between revisions
Appearance
Makes more sense this way |
|||
Line 17: | Line 17: | ||
* Release December 30th | * Release December 30th | ||
== Beta 3 (2. | == Beta 3 (2.8.92) == | ||
* Tagging January 4th | * Tagging January 4th | ||
* Release January 7th | * Release January 7th |
Revision as of 20:07, 20 November 2014
See also: Feature Plan, Quality Control
Freezes
Master is never frozen for features or strings. The branch calligra/2.9 is always frozen for features or strings.
Testing
Beta 1 (2.8.90)
- Tagging and branching (calligra/2.9) December 6th (no big merge on that day)
- Release December 10th
Beta 2 (2.8.91)
- Tagging December 27th
- Release December 30th
Beta 3 (2.8.92)
- Tagging January 4th
- Release January 7th
Stable releases
2.9.0
- Tagging December [???]
- Release December [???]
2.9.1
- Tagging [???]
- Release [???]
2.9.2
- Tagging [???]
- Release [???]
2.9.3
- Tagging [???]
- Release [???]
2.9.4
- Tagging [???]
- Release [???]